What are liquidated damages in a construction contract?

Liquidated damages are an amount the contractor pays the client for each day the works go past the date for practical completion. The rate is set in the contract before work starts, as an estimate of what a late finish will cost the client, and an extension of time moves the date they are counted from.

Liquidated damages are a fixed amount the contractor pays the client for every day the works finish late. The rate is written into the contract before work starts, so both sides know from the first day what a late finish will cost.

They are often shortened to LDs. Standard building contracts, including AS 4000, provide for them, and the rate itself sits in the contract details for each project.

The rate

The rate is meant to be a genuine estimate of the loss a late finish would cause the client. For a school, that can mean hiring temporary classrooms, paying for extra supervision or keeping its own project team on longer than planned. For a council, it can be the hire fees lost from a clubhouse that misses the season.

It is not a fine. A rate set far above any loss the client could suffer can be challenged as a penalty, so the figure is worked out from the client's own costs rather than picked to frighten tenderers.

When they apply

LDs start on the day after the date for practical completion. They stop when practical completion is reached, and every day in between is counted at the contract rate.

The date for practical completion is the one in the contract, adjusted for any extensions of time granted along the way. What has to be finished by then is set out in what happens before practical completion.

Extensions of time

A granted extension moves the date, so LDs start later. The usual grounds are delays the contractor did not cause, such as a variation, wet weather beyond the allowance or late access to the site.

That is why delay notices matter. A contractor who gives notice on time, setting out the cause and the effect on the programme, has its position on record well before anyone counts days. The process is covered in how extensions of time and delay costs are handled.

The figure in the tender documents

Every tenderer sees the LD rate before it prices. A rate well above the client's likely loss pushes every price up, and it does nothing to make a late finish less likely.

Some contracts also cap the total LDs at a share of the contract price, written in alongside the rate.

Fixed windows

On a school holiday project, money does not fix a late finish. The school needs its rooms on Day 1.

So the effort goes into the planning before the break: the scope is settled and materials are ordered early, so construction can carry on through the whole window. Monument upgraded the amenities and changerooms at Georges River College Peakhurst and Penshurst over the end-of-year holidays, and both were handed over on time, ready for Day 1, Term 1. The method is in how works are delivered in the school holidays.