What should a scope of works include for a school or council project?
A scope of works describes the work the contractor is to price and deliver, what is excluded, the standards it must meet and the conditions it will be carried out under. For a school or council site, it also sets out the operating constraints, such as which areas stay in use, the hours for noisy work, the access for deliveries and the handover date.
On a school or council project, the scope of works sets out the work being priced, what is left out, the standards it must meet and the conditions on site. Every tender price, variation and final inspection goes back to it.
It sits beside the drawings and the specification. The drawings show what the work looks like, and the scope says what is included and how it has to be carried out.
The work itself
The scope lists each area and each element of the work, from the rooms to be refurbished to the structures to be built and the surfaces to be replaced. Where quantities are known, it states them, and where they are not, it says how that part will be priced.
Exclusions and work by others
Anything the client will handle itself is named, such as loose furniture, IT equipment or an audio-visual system supplied under a separate contract. Each of these touches the contractor's work somewhere, so the scope says who connects what.
A gap between two scopes is where a project loses time.
Standards and guidelines
The scope names the standards the work must meet and the edition of each. On a NSW public school, that includes the Department of Education's facilities standards, covered in the NSW school facilities standards. On a sports facility, it can include the sporting body's own guidelines.
Site conditions
What the client knows about the site goes in with the scope: hazardous materials registers, service locations, surveys and as-built drawings. The more of it a tenderer can see, the fewer allowances it has to make, as explained in what a client should provide at tender.
Operating constraints
On a site that stays open, this section shapes the price as much as the work does. It sets out which areas stay in use, the hours for loud or high-risk work, the access route for plant and deliveries, the screening workers need, and dates such as exams and events when work stops.
Programme and handover
The scope gives the start date, any stages and the date the work must be handed back, whether that is Day 1, Term 1 or the start of a season. It also lists what has to be handed over at the end, from certificates to manuals.
Approvals
Some work needs approvals before it can start, such as a road-opening permit for a new driveway onto a council road. The scope says who obtains them.
Monument has obtained council approvals and road-opening permits on the client's behalf, including for the new accessible drop-off zone and driveway at Yates Avenue Public School in Dundas Valley. Permits are explained in what a road opening permit is.
Performance briefs
On a design and construct project, the scope reads more like a brief. It describes what the finished space has to do, and the contractor designs it to suit. Monument's design and construct work includes the Cabramatta Public School canteen refurbishment and the Fairvale Public School staffroom and uniform shop.