How is an office fit-out delivered while staff keep working?

The floor is divided into zones and the fit-out moves through them one at a time, with staff moved out of each zone before work starts there and back in once it is finished. Loud work, service cutovers and large deliveries go outside office hours, and each work zone is sealed against dust and noise. Monument's fit-out and refurbishment work includes council interiors and school administration buildings.

An office that stays in use is fitted out in zones. Staff move out of one zone while it is built, then move into the finished space so the next zone can start.

The rest of the floor keeps working the whole time. Everything about the method is aimed at the people on the other side of the partition.

Zones and moves

The floor plan is split into zones that can each be closed off without cutting the rest of the office off from its exits, kitchens or toilets. Each zone has its own start date, finish date and move date in the programme.

The people in a zone need somewhere to go while it is built. That swing space is set up and ready before they leave, as covered in decanting during works.

Hours

Office hours set the rhythm of the work. Demolition, core drilling and cutting go outside them, at night or on weekends, while quieter tasks such as painting preparation and joinery installation can go ahead during the day behind sealed partitions.

The building manager's rules decide the rest. Lifts, the loading dock and noisy work are usually booked through them, and in a council building, any public counter has to keep its service hours.

Power and data

Staff need their computers on the morning after any change. Power and data cutovers are planned outside hours and tested before the zone reopens, with the client's IT team on hand for the switch.

How electrical work is staged in an occupied building is set out in electrical upgrades in an occupied building.

Dust and noise

Each zone is sealed from floor to ceiling, with its own entry for trades and materials. Cutting is done with extraction, floors outside the zone are protected, and the route from the zone to the lift is cleaned at the end of each shift.

Furniture, joinery and IT

Joinery is made off site and installed in as few visits as possible. Loose furniture and IT equipment often come from separate suppliers, so their delivery dates are fixed into the programme alongside the fit-out.

Handover by zone

Each zone is cleaned, checked and handed back before the next one starts. Defects found at that point are fixed while the trades are still nearby, rather than at the end of the whole project.

The method is the staged approach described in staged handover on a live site.

Monument's record

Council interiors, school administration buildings, libraries and canteens all sit within Monument's fit-out and refurbishment capability. Its first projects after it was founded in 2006 were commercial office and hospitality fit-outs, and in 2008 it delivered the Sega Australia and WWE Australia headquarters.