What is possession of the site, and how does it work when the site stays open?
Possession of the site is the client handing the contractor control of the area where the work will happen. On a school, park or public building that stays open, possession covers a fenced construction zone rather than the whole property, and it is often given in stages, with each area handed back as it is finished.
When a contractor takes possession of the site, the client hands over control of the work area. From then until it is handed back, the contractor controls that area and answers for what happens inside it.
Standard building contracts, including AS 4000, require the client to give the contractor possession of enough of the site to start work by an agreed date. A late handover of the site counts as a client delay, and it can entitle the contractor to more time.
A fenced zone
On a live site, the contractor rarely takes the whole property. Possession covers a fenced construction zone, and the rest of the school, park or public building stays with the client and the people who keep using it every day while the work goes on behind the fence.
The boundary is marked on a site plan and agreed before work begins. Inside it, the contractor controls access and safety, while outside it the school, council or facility carries on as normal. Monument keeps construction zones physically separated from occupants.
Possession in stages
Larger works on a live site are broken into stages so the facility keeps operating. Each stage has its own date for possession and its own date for handing the area back, and the programme shows both.
One late handback delays the next stage. The stage dates are therefore watched as closely as the final completion date, as covered in staged handover on a live site.
Shared areas
Some ground belongs to both sides, such as a driveway used by deliveries and by parents, or a path that passes the hoarding. Who uses it, and at what times, is agreed in writing before work begins.
A delivery booked for the same half hour as the school drop-off is the kind of clash that agreement avoids.
Condition at possession
A record of the area's condition when it is handed over protects both sides. Dated photographs and notes show what was already damaged, so a crack or a broken paver is not argued over at the end.
That record is often a formal survey, explained in dilapidation surveys before work starts.
Holiday works
On a school holiday project, both dates come from the school calendar. Neither one moves. Possession comes as the break begins, and the area has to be handed back complete for the first day of the new term.
With so little room on either side, the scope is settled and the materials are ordered before possession, so construction can carry on without a break.
Rail possessions
On the rail network, the word means something narrower: a period when a section of track is closed to trains so work can be carried out safely. That kind of possession is explained in what a rail possession is.