What is a request for information (RFI) on a construction project?

A request for information, or RFI, is a written question the contractor sends when the drawings or specification are unclear, conflict with each other or leave something out. The answer comes back in writing and goes on the project record, and if it changes the work, it is dealt with as a variation under the contract.

When the drawings do not answer a question, the contractor puts it in writing as a request for information, or RFI. The client's side replies in writing before the work it affects goes ahead, and both the question and the answer stay on the project record.

Every project has them. A set of drawings describes work that has not been built yet, and some questions only appear once the trades start planning it in detail.

Common causes

  • a drawing and the specification describe the same item two different ways
  • a dimension or a detail is missing
  • the existing building does not match the drawings, which is common in older schools and halls
  • a specified product is no longer made
  • a service turns up where the drawings show none

A useful RFI

A good RFI asks one question and makes it easy to answer. It names the drawing or clause, describes the problem in a sentence or two, and attaches a photo or a marked-up sketch.

Where the contractor has a sensible answer in mind, it proposes one. It also gives the date the reply is needed by, and why, so the designer can see which questions are holding up work on site.

The answer

The reply comes from the designer or the client's representative, through whoever administers the contract. On many projects that is the superintendent, whose role is set out in how a contractor works with a superintendent.

An answer given verbally on site is confirmed in writing afterwards. Months later, nobody remembers a conversation by the hoarding in quite the same way.

RFIs and variations

An RFI asks a question. It does not approve extra cost. If the answer adds work, removes it or changes it, that change is instructed and priced under the contract's variation clause, as covered in how variations are managed.

Keeping the two apart protects both sides. The client knows what it has approved, and the contractor knows what it has been told to build.

Response times

A slow answer holds up the trade waiting on it. On a school holiday project, days lost to an open question cannot be won back at the end of the break.

So the drawings are read closely at the start, and the questions go in before the trades arrive, not on the morning they need the answer.

Tender clarifications

During a tender, questions go to the client's named contact. The answers are issued to every tenderer as an addendum, so all the prices rest on the same information.

The register

Every RFI is numbered and logged with its date, its status and its answer. Monument keeps project information on secure cloud-based software from tender through to handover and the end of defects, so a question asked in the first month can still be found at the last. How that record is kept is set out in document control on a construction project.