Which school works suit the holidays, and which can be done during term?
Work that would close a space the school needs every day, or keep loud work and heavy plant near classrooms for weeks, suits the holidays, where construction can carry on without a break and hand back for Day 1, Term 1. Work that can be fenced off, staged and kept apart from students can be done during term, as Monument did with asphalt resurfacing at Athelstane Public School.
Work that would shut a space the school needs every day belongs in the holidays. Work that can be fenced off, staged and kept apart from students can go ahead during term.
Plenty of projects use both. The loudest stage goes into a break, and the rest is done during term, with each area handed back as it is finished.
Term-time works
During term, the work is planned around the school timetable rather than the other way around. Monument breaks it into stages behind secure hoarding and fencing, gives plant and deliveries their own access, keeps full-time supervision on every machinery movement near students, and schedules noisy or high-risk activities away from teaching and movement times.
That suits work with a clear edge to it. Monument resurfaced the asphalt at Athelstane Public School in Arncliffe during term, completed the staff amenities at Como West Public School during normal operating hours, and delivered a complete library fit-out at Cambridge Park High School while the school kept operating. The day-to-day method is set out in construction on an operating school.
Holiday works
A school can lose a corner of the playground for a few weeks and carry on. Losing its only changerooms, or a whole amenities block, is much harder to work around while students are there.
The holidays give a clear site and a finish date that cannot move. Monument upgraded the amenities and changerooms at both campuses of Georges River College, Peakhurst and Penshurst, over the end-of-year holidays, and both were handed over on time, ready for Day 1, Term 1.
The questions that decide it
- Can the work area be closed off without stopping part of the school?
- How much of the work is loud or dusty, or needs heavy plant near classrooms?
- Can the space be handed back in stages, or is it only useful once it is finished?
- Are there exams or school events in the term that would halt work for days?
- Does anything need to be ordered weeks before it is installed?
The holiday window
A holiday project is decided before the break starts. The scope is settled and the materials are ordered ahead of time, so construction can carry on through the whole break and finish before the new term.
Anything made to order is ordered early, because a late delivery in a fixed window can cost the handover. The approach is set out in how works are delivered in the school holidays for a Day 1, Term 1 handover.
The school calendar
Term-time work also has to fit around the school's own dates. Exams, assemblies and sports days change what can happen on site, and loud work near an exam room stops for the length of the exam.
The calendar is easier to plan around when the school shares it before the programme is set. Working around exams and sensitive periods covers how those dates are agreed.