What are shop drawings, and why are they approved before anything is made?
Shop drawings are the maker's own detailed drawings of an item, such as joinery, a balustrade or a lift, showing exactly how it will be built, finished and fixed. They are checked against the design and the site before manufacture starts, together with samples of the finishes, because an error found on paper costs far less than one found at installation.
A fabricator does not build from the design drawings alone. It prepares its own shop drawings, showing exactly how the item will be built, finished and fixed, and those drawings are checked before anything is made.
The order matters because of what happens after. Once steel is cut or a cabinet is built, a wrong dimension is expensive to fix and slow to replace.
Items that need them
- joinery and built-in furniture
- steel balustrades, handrails and gates
- shade structures and canopies
- lifts and chair-lifts
- windows, doors and glazing
- signage
The review
The designer or the client's representative checks the shop drawings against the design. Dimensions, materials, finishes and fixings are all looked at, along with how the item sits against the walls, floors and services around it.
Comments are marked up and returned, and the maker revises and resubmits until the drawings are accepted. Many contracts state that this review does not take away the contractor's responsibility for the item meeting the contract.
Site measure
In an older building, walls are often out of square and floors out of level. So the space is measured on site before the shop drawings are finished, and the item is drawn to fit what is there.
Joinery drawn only from the tender drawings can arrive a few millimetres out of the space it was made for, and in a school that gap is enough to stop a cabinet going in. How joinery is delivered on a school site is covered in joinery in a school environment.
Samples
Finishes are approved from a physical sample rather than a brochure or a screen. Laminate, tiles, paint colours and floor coverings are each signed off, and the approved sample stays on site as the standard the installed work is checked against.
Public ramps and stairs
A balustrade on a public ramp has to meet access and safety requirements as well as the design. Its shop drawings show the heights, the gaps in the infill and how each post is fixed, so those details are settled before fabrication.
At Parry Park in Lakemba, Monument delivered a clubhouse changeroom and accessible ramp upgrade that included a compliant disabled access ramp and balustrading. What goes into a public balustrade is set out in balustrades and handrails on public sites.
Holiday projects
Fabrication starts only once the shop drawings are accepted. That review time is part of the lead time, and on a school holiday project it has to finish well before the break begins.
Lifts and chair-lifts are made to order, so their drawings are approved before the order is placed. Monument installed an accessible chair-lift at Connells Point Public School, giving compliant access from the school hall to the stage. Ordering early is explained in long-lead items and early procurement.