How should a school or council compare construction tenders?
Against the same scope first, then on everything around the price: the exclusions and qualifications, the allowances, the programme against the handover date, the methodology for keeping the site operating, the people named to lead the works, and the contractor's certification, prequalification and record. A low price is only low if it covers the whole scope.
Put every tender on the same footing before looking at the price. A tender that leaves out part of the scope can look lower while costing the client more by the end of the project.
After that, the comparison moves to everything that sits around the price. On a site that stays open, much of it comes down to how the work will be carried out.
The scope
Each tender is read against the scope of works and the drawings. Anything a tenderer has left out is listed, along with what it would cost the client to add back.
A tender that excludes traffic management or hazardous materials removal is pricing a smaller project. The client still has to pay for those items somewhere.
Exclusions and qualifications
Qualifications are the conditions a tenderer attaches to its price. They are set side by side so the differences show at a glance, and any that are unclear are raised in writing before award, with the same question put to every tenderer it affects.
Allowances
Provisional sums and prime cost items stand in for costs nobody can fix at tender. Two tenders with different allowances for the same item cannot be compared until those allowances are levelled, as explained in provisional sums and prime cost items.
The programme
Each programme is checked against the date the client needs, such as Day 1, Term 1 or the start of a sporting season. A programme that reaches the date on paper but leaves no room for approvals, long-lead items or wet weather is a warning sign.
The methodology
On a school, park or public building, the methodology shows whether the tenderer has planned for the people who stay on site. It covers the staging, the separation of the work zone, the routes for deliveries and the times for noisy work.
A methodology written for this site, naming its buildings and its timetable, says more than a general one. The contents of a good one are covered in what a construction methodology should show for a live site.
The people
The tender names who will manage the project and who will supervise the site each day. Those people matter more than the company profile, because they are the ones the school or council will deal with every week. Monument's delivery is director-led, with its directors on site and on the calls.
Standing and record
Prequalification, certification, licences and insurances confirm the contractor can be engaged for the work. Monument, for example, is prequalified under NSW Government Scheme SCM 0256 (up to $1M) and NSW Government Scheme SCM 1461 ($1M to $9M), and is certified to ISO 9001, ISO 14001 and ISO 45001.
Referees from similar sites add what documents cannot. A school principal who has had a contractor working beside classrooms knows how that contractor behaves when the bell goes. What to check is in what a principal contractor should hold.
The weighting
How price is weighed against the other criteria is settled before the tenders are opened. Each tender is then scored against that plan, and the reasons for each score are written down.