What are enabling works, and why do they come before the main build?
Enabling works are the early works that get a site ready for the main construction, such as locating and moving underground services, demolition and clearing, temporary facilities for the people being moved out, new site access and making the site safe. Doing them first takes the unknowns out of the site before the main programme depends on it.
Before the main build starts, the site has to be cleared of what is in the way, under the ground or still in use. That early work is known as enabling works. It comes first so the main programme starts on a site with fewer unknowns.
Some projects buy enabling works as a separate early contract, and others treat them as the first stage of one contract. Either way, a problem found now costs less than one found once the main build is under way.
What they include
- locating, protecting or moving underground services
- demolition and strip-out of what is being replaced
- removal of hazardous materials found in the old structure
- tree protection, and removal where it is approved
- temporary classrooms or offices for the people being moved
- new or temporary site access, hoarding and fencing
Services
An unknown pipe or cable found halfway through a dig stops work while it is dealt with. Locating services early, and moving the ones in the way, gives the main build a clear site. How that is done is covered in how underground services are located and relocated.
Demolition
Taking out the old structure often shows what the drawings could not. A slab can be in worse shape than anyone expected, or a wall can turn out to carry load. Found during enabling works, those problems can be designed for before the main build starts.
The controls for demolition near occupants are in demolition and strip-out in an occupied building.
Temporary accommodation
On a school or council site, the people in the old building need somewhere to go before it closes. Temporary classrooms or offices are installed, connected and ready first. The move happens before the main works need the space.
Fire-damaged buildings
Some projects start with a building that is unsafe to enter. After a fire, the works begin by making the site safe and remediating the damage to its internal fabric and infrastructure. Only then does the upgrade begin.
Monument delivered this sequence at Cranebrook High School. A fire-damaged library was made safe, remediated and brought back into service with new ceiling and floor linings, interactive audio-visual works, lighting, security and furniture. The project is described in how a fire-damaged school building is remediated and rebuilt.
School sites
Heavy plant and long service shutdowns are easiest to manage when the grounds are empty. So on a school, the noisiest enabling works often go into a holiday break. The main works then start on a ready site, with less disruption left for term time.