What happens at a construction pre-start meeting?
The client and the contractor meet before work begins on site to agree how the project will be carried out: the contacts, the programme, the site boundary and access, safety and inspections, and how changes and reports will be handled. On a school or public site, it is also where the occupants' timetable and calendar are written into the plan.
Before anyone starts work on site, the client and the contractor sit down to agree how the project will be carried out. The pre-start meeting turns the contract and the tender methodology into a plan both sides can work to from the first day.
On a site that stays open, it carries extra weight. It is where the school, council or facility tells the builder what has to keep working while construction goes on around it.
Who attends
The client's side usually brings its project manager or representative, plus the person who manages the site day to day, such as a principal, a business manager or a facility manager. If a superintendent is appointed under the contract, they attend as well.
The contractor brings the project manager and the site supervisor who will lead the works. Monument's delivery is director-led, with its directors on site and on the calls.
The agenda
A typical pre-start covers:
- the contact for each side, and who can make decisions
- the programme, its stages and any fixed handover date
- the site boundary, hoarding and fencing, and the route for plant and deliveries
- the times when noisy or high-risk work can be done
- inductions, the WHS management plan and how incidents are reported
- inspections and hold points the client wants to attend
- permits and approvals still to come
- how variations, questions and progress reports will be handled
The site boundary
On a live site, the most useful thing the meeting produces is a clear line between the construction zone and everyone else. Monument keeps construction zones physically separated from occupants. On a school, that means secure hoarding and fencing, separate access for plant and deliveries, and full-time supervision of machinery movement near students.
The line is drawn on a plan and walked on site, so there is no doubt about it on day one. How that set-up works is covered in site establishment, hoarding and fencing.
The client's calendar
The client knows dates that no drawing shows, such as exams, events, sports days and the end of term. Those dates go into the programme at the start, instead of surfacing in the week a crane is already booked.
Safety documents
The WHS management plan and the first safe work method statements are ready before work begins, so the meeting can confirm them rather than wait for them. What the plan holds is covered in what a WHS management plan is.
The record
The meeting is minuted, and the minutes become the first entry in the project record. Monument keeps project information on secure cloud-based software from tender through to handover and the end of defects, so what was agreed at the pre-start stays on file for the life of the project.
Contact after the meeting
Each side leaves with one named contact. Monument manages projects through a single point of contact, who keeps the client informed as the works move from one stage to the next, as described in how site users are kept informed.