What is the difference between a lump sum and a schedule of rates contract?
Under a lump sum contract, the contractor agrees one price for a defined scope and carries the risk on quantities. Under a schedule of rates contract, the parties agree a rate for each unit of work and the client pays for the quantity measured, so the client carries that risk. A lump sum suits work that can be drawn in full, and a schedule of rates suits work whose extent is unknown until it starts.
The difference is who carries the risk on quantities. A lump sum is one price for a defined scope, while a schedule of rates is a set of unit prices paid against what is measured on site.
Standard contracts such as AS 4000 can be set up either way, or with a mix of the two.
Lump sum
The contractor prices the scope shown in the drawings and specification and agrees to deliver it for that sum. If the work takes more concrete or more labour than the contractor allowed, that cost is the contractor's to carry.
The price changes only through the contract, mainly through variations when the client changes the scope, as covered in how variations are managed.
A lump sum suits work that can be drawn and specified in full before tender, such as a new amenities building, a library fit-out or a canteen refurbishment. The client knows the price at the start, which suits a fixed capital budget.
Schedule of rates
Each tenderer prices a list of units, such as a rate for each square metre of asphalt, each lineal metre of kerb, each tonne of spoil or each item installed. The work is measured as it is done, and the client pays the measured quantity at those rates.
This suits work whose extent cannot be known at tender. Repairs spread across many sites, maintenance carried out over a period and work hidden in the ground are all easier to price this way than as one sum.
The mix
Plenty of projects use both. The defined work is a lump sum, and the uncertain parts carry rates.
Asphalt resurfacing on a school playground shows why. Resurfacing often includes replacing the sub-base under the old asphalt, and how much needs replacing is only clear once the old surface is lifted. A rate for that part lets it be paid for as found, rather than guessed at tender. The method is in how asphalt resurfacing is done on a live school playground.
Measurement
A schedule of rates is only as fair as its measuring. The contract sets how each unit is measured, and both sides agree the quantities as the work goes, with photos and site diary entries behind them.
Tender comparison
Lump sum tenders compare directly. Schedule of rates tenders are compared by applying each tenderer's rates to the same estimated quantities, so a low rate on a small item cannot hide a high rate on a large one. Comparison is covered in more detail in how to compare construction tenders.
Monument's work
Monument's projects cover both kinds of scope. They range from buildings such as the Roberts Park Clubhouse at Greenacre to Crown land ground maintenance and asset protection zone works across NSW for the NSW Office of Strategic Lands.
Related
Monument Environments
Boutique principal contractor for NSW government and institutional clients, specialising in construction inside operational environments that cannot be shut down. Established 2006. ISO 9001, 14001 and 45001 certified. Prequalified SCM 0256 and SCM 1461.